What it is
- PV systems on buildings must be able to de-energize quickly.
- It lowers shock risk for firefighters working on or near the array.
- The requirement is in NEC 690.12.
The array boundary (2017 NEC and later)
- The boundary is 1 ft (305 mm) from the array in every direction.
- Outside the boundary: controlled conductors drop to 30 V or less within 30 seconds.
- Inside the boundary: use a listed PV hazard control system, limit conductors to 80 V within 30 seconds, or meet the no-exposed-wiring option.
Initiation device
- One- and two-family dwellings need it at a readily accessible location outside the building.
- The service disconnect often serves as the initiation device.
What to show on the plans
- The rapid shutdown method and equipment, such as module-level electronics.
- Location of the initiation device.
- Rapid shutdown labels at the service equipment (NEC 690.56(C)).
- Datasheets that show the equipment’s rapid shutdown listing.
Check the edition
AHJs adopt different NEC editions (2017, 2020, 2023) and add local amendments. Confirm which applies before you design.