What Goes Into a Permit-Ready Solar Plan Set
The sheets most AHJs expect to see, and what each one needs to show.
TriventX Engineering Team ·

Cover sheet
- Project address, owner, and contractor details.
- System size in kW DC and kW AC.
- Code editions the design follows.
- Sheet index.
Site plan
- Property lines, buildings, and the array location.
- Main service panel, meter, and disconnect locations.
- Conduit routing between equipment.
Roof and array layout
- Module placement on each roof plane.
- Fire code pathways and setbacks, dimensioned.
- Roof slope, azimuth, and attachment locations.
Structural and attachment details
- Racking and attachment details.
- Rafter size, spacing, and span.
- Load checks for wind and snow where the AHJ asks for them.
Electrical diagrams
- Single-line or three-line diagram.
- Conductor, conduit, and overcurrent protection sizing.
- Grounding, bonding, and the rapid shutdown method.
- Interconnection point and busbar calculation.
Labels and datasheets
- Required warning labels and placards, with locations.
- Datasheets for modules, inverters, racking, and batteries.
Good to know
Every AHJ is different. Some want structural letters, others accept SolarAPP+ for instant approval. Always check the local checklist first.